Finland

Enabling framework

Bad

Summary

Updated December 2022

Finland has adopted legislation that aims to transpose EU provisions on energy communities. So far, the government has only adopted one definition of ‘Local Energy Communities’, which is more connected to the CEC definition than to the REC definition. Because of this gap, there are no provisions that relate to the enabling framework for RECs. The only area that has been addressed is electricity sharing via virtual net metering. Some responsibilities of the DSO have been elaborated in this regard. Overall, the Finish government has not put in place any meaningful steps towards building an enabling framework, although there is a government working group that was established to look at the issue and develop the framework further, in line with its transposition requirements.

Detailed assessment

Assessment of potential and barriers for the development of energy communities

Average

The Government commissioned a study on the unjustified barriers concerning self-consumption and energy communities in 2019. If unjustified barriers were found, an assessment should have been made as to whether they can be removed.

A new Working Group was set up in September 2022 for 6 months by the Ministry of Economic Affairs and Employment to identify regulation changes needed to develop a coherent piece of legislation on the different types of energy communities as those are not yet fully transposed.

Inclusion in planning (NECPs, regional/local planning, RAAs, etc)

Average

NECP reporting on enabling frameworks

Not addressed in the transposition. Member States are required via the Governance Regulation (2018/1999) to report on their enabling frameworks for RECs by 15 March 2023.

Fair, proportionate and transparent procedures to become licensed for different activities

Average

The DSO must register the LEC according to section 15 of the Decree 839/2021 after receiving the relevant information and its updates. The DSO must then notify the central information exchange unit of electricity trade (Data hub) no later than 7 days and no earlier than 90 days before the start of the credit calculation. The compensation calculation must start within the 14 days of receiving this information from the LEC, unless the LEC was delayed in its notification.

Non-discriminatory treatment and removal of regulatory and administrative barriers

Bad

Non-discriminatory treatment as market participant

Not addressed in the transposition.

Removal of unjustified regulatory & administrative barriers

Not addressed in the transposition.

Supportive framework and incentives for energy sharing

Average

DSO responsibilities

The Decree transposing energy community provisions elaborates some duties for DSOs regarding facilitation of energy sharing. First, DSO must register the LEC according to section 15 of the Decree 839/2021 after receiving the relevant information and its updates. Second, the DSO is responsible for measuring electricity usage locations of the LEC’s members or shareholders. The DSO must also report net metering information of the LEC to the electricity trader's centralized information exchange centre for the purpose of organizing the internal credit calculation of the balance settlement period. The DSO must also notify the central information exchange centre if the internal netting of the balance settlement period for consumption and production is applied to the electricity usage point connected to its distribution network.

Incentives (tariff, tax exemptions, etc.)

Not addressed in the transposition.

Support to help low-income and vulnerable households access energy communities

Bad

Not addressed in the transposition.

Tools to access information

Bad

Not addressed in the transposition.

Regulatory capacity building/support for public authorities

Bad

Not addressed in the transposition.